- Proposal
- 7 units (5 SF + 1 two-unit duet)
- Affordable
- Duet designated low-income
- Site
- 5.34 acres; 20 parking spaces
Status
Applicant Allen Qin. EIR by David J. Powers. NOP comment period Jan 16–Feb 15, 2026; scoping meeting Feb 3, 2026. The city project page, checked October 10, 2026, says the Draft EIR is anticipated to be complete in late fall. It does not name a month, and no Draft EIR is posted. Comments: krathbone@saratoga.ca.us, subject “22200 Mt Eden Road Project”.
Why CRED is watching
- Draft EIR not posted
- City page says late fall, with no month
Timeline
- Mar 11, 2024SB 330 preliminary application
- Jul 29, 2024Formal application
- Dec 23, 2024Deemed complete
- Feb 5, 2025Inconsistency letter
- Jan 16, 2026NOP comment period opened
- Feb 3, 2026EIR scoping meeting
City packets last checked September 18, 2026. Drive folders and packet PDFs live on the city site. CRED does not host applicant documents.