- Proposal
- 69 condominium / townhome units in 12 buildings
- Affordable
- 14 ADUs restricted affordable
- Site
- 3.85-acre vacant site; access at Marshall Lane intersection; 111 trees proposed for removal (71 protected)
Status
City project page, checked October 26, 2026: the Planning Commission unanimously rejected the project on October 14, 2026, on the basis of public safety. The applicant appealed on October 15. The appeal hearing is tentatively set for November 18. Adopted October 14 minutes were not posted when this was checked. The city page still describes 55 townhomes and 14 accessory dwelling units on 3.85 acres.
Why CRED is watching
- 69 units on 3.85 acres
- 111 trees / 71 protected on the city page
- Marshall Lane access
Timeline
- Mar 18, 2024SB 330 preliminary application
- Sep 10, 2024Formal application
- Jun 12, 2025Deemed complete
- Jul 11, 2025Inconsistency letter
- Sep 9, 2026Planning Commission hearing continued
- Oct 14, 2026Planning Commission rejected the project, per the city page
- Oct 15, 2026Applicant appealed
- Nov 18, 2026City page: Council hearing tentatively set
What CRED is doing next
- Watch for the posted Council agenda. The city page says November 18 is tentative.
City project page (opens in a new tab)October 14 Planning Commission agenda (opens in a new tab)City agenda center (opens in a new tab)Comment kit
City packets last checked September 18, 2026. Drive folders and packet PDFs live on the city site. CRED does not host applicant documents.