- Proposal
- 12 townhomes
- Affordable
- 2 units (reduced from 3 under AB 1893)
- Site
- 66,211 sq ft; three-story / max 47 ft; 29 parking spaces
Status
City (Apr 17, 2026) is reviewing the level of environmental analysis required. Hearing TBD.
Why CRED is watching
- 47-ft three-story townhomes
Timeline
- May 16, 2024SB 330 preliminary application
- Apr 4, 2025Deemed complete
- May 1, 2025Inconsistency letter
City packets last checked September 7, 2026. Drive folders and packet PDFs live on the city site. CRED does not host applicant documents.