- Proposal
- 96 units in 26 buildings on a 7-lot subdivision
- Affordable
- 13 low-income units
- Site
- 25.05 acres; average slope 16.7%; most access from Chiquita Court, 15-unit building from Comer Drive
Status
Ferris Development for David L. House. Formal submittal raised units 85→96 and lots 5→7. Three-story buildings (one four-story). City (Apr 17, 2026): EIR paused while the applicant prepares additional geotechnical studies. Scoping session will be scheduled only when the applicant asks the city to resume.
Why CRED is watching
- 96 hillside units / 16.7% slope
- Geotechnical pause
- Comer Drive access for Building Type D
Timeline
- Feb 15, 2024SB 330 preliminary application
- Aug 12, 2024Formal application
- Jan 16, 2025Incomplete letter
- May 14, 2025Deemed complete
- Jun 12, 2025Inconsistency letter
- Apr 17, 2026City: EIR paused for geotechnical studies
City packets last checked September 7, 2026. Drive folders and packet PDFs live on the city site. CRED does not host applicant documents.